New Initiatives

Modernization work for Tungabhadra Board Right Bank Canals

RBHLC (105 Kms.)
Km. 0.00 to  14.00 2016-17 : Work has been completed
Km.15.00 to 105.00 2017-18 : 30% Work completed
 2018-19 : Works under progress – completed upto 80%
PC (20 Kms.)
Km.0.00 to 20.00 2018-19: Works under progress – completed upto 25%
RBLLC (250 Kms.)
Km.0.00 to 22.00 Shortly will be taken up.

Due to the completion of modernization of RBHLC upto 80% from Km.0.00 to 105.00, the velocity of flow has improved and indented discharges are being delivered to both member States.