Procured

33

Fabricated

24

Dismantled

20

Erected

12

Detailed Progress
Description Total Completed Progress (%)
Material Procured 33 33
100%
Fabrication of gates 33 24
73%
Dismantling of gates 33 20
61%
Erection of New gates 33 12
36%