Modernization Works of RBHLC TB Board
Author: tbboard
Annual Report 2011-12
Annual Report 2010-11
Constitution of board
The Tungabhadra project was taken up by then states of Madras and Hyderabad during February 1945. With the formation of Andhra State Act 1953, certain areas of the project of the right side of the river belonging to the then madras state were transferred to the then Mysore state and the project became a venture of the then states of Mysore, Andhra. This resulted in more than 55 percent of irrigated area on the right bank of the river falling in Andhra & the reservoir with the head reaches of the canal system lying in the state of Mysore .This situation warranted constitution of an independent body to look after the timely completion of the approved project, its maintenance and oversee distribution of benefits to the states.
Subsequently ,as per the Andhra State Act,1953,President of Indian was authorized to give directions for the completion of the project and its operation and maintenance there after .Accordingly, Under a presidential order, Tungabhadra Board was constituted with effect from 1st oct,1953 vide notification No DW II -22(129) Dated 29 th sep,1953 of the then ministry of irrigation and power.
The Board constituted of chairman appointed by government of India & six members were chief engineers of both irrigation and power department of the government of Andhra, Mysore and Hyderabad .Chairman of the central water And power commission was appointed the chairman of the board in addition to his normal duties .The board was entrusted with the task of completion of the Project and to deal with all matters relating to works, which were common to both the states of Andhra and Mysore.
The board was reconstituted with effect from 15 march, 1955 vide notification No DW VI (4) (9) Dated 10-3-1955 of the then Ministry of irrigation and power (copy at Annexure 2.1).The reconstituted Board consisted of a chairman appointed by the government of India, Andhra, Mysore and Hyderabad. After the reorganization of the states in 1956, the Hyderabad Government representative was deleted from Board vide Notification Np.39(25)/56 DW .VI dated 1.11.1056 of then ministry of irrigation and power.
Earlier the center line of the Tungabhadra River was the boundary on then states. With re-organization of states, the center line of river no more remained the boundary and the canal on the right bank meandered through the states of Andhra Pradesh and Karnataka
Present Composition Of Board
The present composition of the Tungabhadra Board is as follows:
Present Composition Of Board
Chairman(Nominated by GoI) Chief engineer, Krishna & Godvari Basin, central water commission, Hyderabad
Member (Representing GoI) Finical Adviser and joint Secretary ,Ministry of water Resources, New Delhi
Member (Representing GoAP) Engineer-in-chief, (Irrigation),Irrigation & CAD Dept., Hyderabad
Member (Representing GoT) Engineer-in-chief, (Irrigation),Irrigation & CAD Dept., Hyderabad
Member (Representing GoK) Secretary to government, Water Resources Department, Government of Karnataka, Bangalore.
Chairman:
Shri P.Ramachandra Rao,
Chairman,Tungabhadra Board and Chief Engineer(KGBO),
Central Water Commission,
H.No.11-4-648,
K.G.Bhavan,A.C.Guards,
Hyderabad.
Member of Government of India
Shri Sunil Kumar Kohli
Member of Government of Andra Pradesh :
Shri Aditya Nath Das
Member of Government of Karnataka
Shri B.G.Guruparaswamy
Function of the Board
The important functions of the Board, initially laid down were:
Completion of the construction of the sanctioned project;
Regulation of supplies of water and power in accordance with such rules as may be made in this behalf by the Board;
Maintenance of canals and other works common to both the states of Karnataka And Andhra Pradesh;
Maintenance of the dam and Reservoir of the project;
Granting of lease of fisheries in the reservoir in the canals:
Proper utilization of land acquired for the purpose of the project; and
Any other function incidental to or connected with the function specified in above clauses.
In the discharge of its assigned functions, the Board exercises power of state Government .Board makes its own rules for the conduct of its own business .The Board appoints a whole time secretary
Tourism
PARKS AND GARDENS
Since completion of the dam, the Board has developed and maintained many gardens and parks, downstream of the dam and in the colonies. The gardens near the dam are attracting many tourists.
Nandanavana Garden
Japanese Park
Deer Park
Birds Aviary
Children Park
Vaikunt Guest House Garden
Circular Park and Triangular Park
Nandanavana Garden
Nandanavana garden was developed soon after the completion of the dam during the year 1956-57. Thisgarden is located just downstream of the dam running parallel to it. It has an area of about 6 acres (2.43 ha) and is designed and developed on the lines of Brindavan Gardens at Krishna Raj Sagar near Mysore. It is well laid with four terraces at different elevations. The first terrace is housing circular type fountain with a Shiva statue at the center. The other three terraces are equipped with fountains of various designs, running parallel and perpendicular to the layout of the garden. This garden has got welll-maintained lawns, Bougain villea on the slopes, seasonal and annual flower beds, Christmas trees, Cyprus plants and topiary arches.
Japanese Park
Japanese Park was developed in the year 1968-69 with a total area of 18 acres (7.29 ha) and is located adjacent to Nandanavana garden. It has got 3 water ponds, namely mango shaped pond, bean shaped pond and children peddle pond which were constructed after 1970. This park has arches, ornamental flowering trees, flowerbeds, etc. A musical dancing fountain was added to the garden in the year 1994 which provides added attraction for visitors. An aquarium was constructed within the garden to provide further choice of entertainment and education for the visitors.
Deer Park
The Deer park is located just by the side of Japanese park. It was developed in the year 1982, with anapproximate area of about 15 acres (6.07 ha). At present , it has got about 70 spotted deer’s, 4 sambars, 4 neelgai, 6 black bucks, 1 chinkora, 30 rabbits and 2 porcupines.
Birds Aviary
A small aviary is housed in the complex of Deer park and was developed in the year 1989. Presently, it has got about 200 pigeons, 4 peacocks, 15 guinea fowl and 10 parrots.
Children Park
Children Park is located in the township area of TB Dam on the main road, and was developed during 1984. It has got latest type of sea-saws, bars, swings and other items for children. The park is exclusively meant for children below 12 years.
Vaikunt Guest House Garden
Garden at Vaikunt Guest House was developed during the year 1960-61. It is a formal garden with well designed fountains, flower bed, topiary arches, flowering trees etc.
Photo vaikunt and garden.
Circular Park And Triangular Park
A Circular Park and a Triangular Park is located just in front of the Administrative building. It was developed at the time of construction of dam. It is also a formal garden with lawns, flowering trees, shrubs, arches etc.
HYDRO-ELECTRIC WING
Although primarily intended as an Irrigation Project, the impounded water in Tungabhadra Reservoir is also utilized to generate power before being let out into the canals for irrigation purpose. The power generated on the left side is entirely used by Karnataka while that generated through two power houses on the right side is shared by states Karnataka and Andhra Pradesh in the ratio of 20:80. One Power House is at the foot of the dam and another at Hampi, 21Km from the dam. The Scheme of generating electricity at these two powerhouses is called “Tungabhadra Hydro Electric Scheme”(TBHES). Work on Dam Power House was taken up in 1951 while that on Hampi power house in 1956. These power houses were commissioned in 1957 and 1958 respectively.
Dam Power House
Dam Power House is located at the foot of the dam. The gross head available at dam powerhouse for generation of power varies from 13m to 26.8m (43ft to 88ft). The four turbines are connected with four steel penstocks, each of 3.3m (11 ft) dia, to the reservoir through butterfly valves. In the first stage, two units each of 9 MW were commissioned on 23rd May 1957 The two units each of 9 MW of second stage were commissioned on 26th February 1964 and 17th June 1964. The total installed capacity of Dam Power House is 36 MW.
The main objective of the project being irrigation, electricity generation is dependent on the water releases made for irrigation requirements in the RBLLC and river assistance to RDS and KC Canal. Water releases vary from time to time as per irrigation demands furnished by the states. During rainy season, especially when the reservoir is nearing 1633ft or isoverflowing, full generation of 36 MW is feasible at the dam power house drawing water at the rate of 5,600 cusecs (153 cumecs) with maximum differential head of 88 ft.(26.8 m).
Hampi Power House
Hampi Power House is fed from the tailrace water from dam powerhouse through the Power Canal. A fore bay is located at the end of this canal which has a storage capacity of 26 Mcft(0.74 Mcum) with normal level of 463.1 m (1,519 ft). The intake structure at forebay has gates, hoists and trash racks. There are two low pressure steel pipe lines (LPPL) each of 5.48m dia (18 ft) and 868.3m in length carrying discharge from forebay to the power house. At the end of each LPPL there is a steel differential surge tank with 18.3m (60 ft) dia and 18.3m (60 ft) in height. There are four penstock pipes each 3.66m (12ft) dia with a maximum discharge capacity of 1,100 cusecs (31.15cumec) two from each of the surge tanks, installed and connected independently to each turbine in the power house.Each penstock is provided with a 3.66 m (12ft) butterfly valve, an air valve at surge tank end and 3.05 m (10 ft) butterfly valve and venturimeter at power house end.
The first unit of 9 MW was commissioned on 10th February 1958 and the second unit of 9MW on 26th March 1958. The remaining two units, each of 9 MW, were commissioned in April and July 1964.
The total installed capacity of Hampi Power House is 36 MW. After generation of power at the Dam Power House water is led into the Power Canal. The discharge carrying capacity of the Power Canal is limited to 2,500 cusecs (70.79 cumec) and hence maximum generation at Hampi Power house is limited to 20 MWs against an installed capacity of 4 x 9 = 36 MW. The generation at Hampi powerhouse is dependent on water discharge through Power Canal. The water discharged from Hampi powerhouse is led into Low Level Canal and is allowed through Gundlakeri escape in case of demand for river assistance.
SHARING OF POWER
The power generated at both the power houses is to be shared in the ratio of 80:20 between Government of Andhra Pradesh and Government of Karnataka.
Tungabhadra Reservoir
Water Management in a reservoir, among others, calls for a fairly accurate assessment of the capacity of the reservoir to store water at various levels. Tungabhadra Reservoir with a drainage area of 28,180 sq.km was designed for storing 133 TMCft. of water and was impounded for the first time in the year 1953. The full reservoir level (FRL) was fixed at RL 1633 ft. Capacity of the Reservoir at various levels was worked out based on the regular contour survey conducted in the river basin upstream of the Dam prior to the impounding of water in the reservoir. The survey was conducted with a contour interval of 10 ft and the capacity of the reservoir computed for every one-foot interval. According to this the Gross capacity of Tungabhadra Reservoir was taken to be 133.0 TMCft., (3766.1 M.cum) at an FRL of 1633 ft. (497.738M).
FISHERIES
The Board has set up a fish farm for producing quality seeds for raising bio mass in available water bodies located in the states of Karnataka and Andhra Pradesh. A part of the seeds so produced are stocked in the reservoir to enhance the fishery wealth of the reservoir. In addition, to facilitate preservation of fish catch, Board is running an Ice-cum-Cold Storage Plant for the convenience of the fishermen of the area. The Board has also established a Fish Net Making Plant to manufacture and supply quality fishnets to the fishermen.
FISH FARM UNIT
The Fish form Unit was setup in the year 1959 in an area of 8.10 ha (20.25 acres). This farm is having earthn ponds of different size ranging from 17m x16m to 94m x 38m and 125 cement ponds of size ranging from 3 x 2 m to 24 x 12 m (10.0 x 6.6 ft to 80.0 x 40.0 ft). A glass jar hatchery unit with a capacity of hatching 50,00,000 eggs per day was commissioned in 1982.
The salient features of Fish Farm Unit are detailed below:
1 | Total water spread area of Fish Farm | 4.70 ha (11.75 acres) area of Fish Farm |
2 | Stock ponds area | 2.29 ha ( 5.73 acres) |
3 | Rearing ponds | 2.15 ha ( 5.44 acres) |
4 | Nursery ponds | 1.00 ha ( 2.50 acres) |
5 | Water supply ponds | 0.13 ha ( 0.33 acres) |
6 | Breeding and hatching ponds | 0.13 ha ( 0.33 acres) |
Every year Fish Form Unit is producing spawn of major carp, common carp and Chinese carp, utilising the parent stock (brood stock) raised in fish farm by hypophysation technique. This method induces the fish to release eggs in stagnant water by injecting pituitary hormone which was first introduced in the unit during 1962-63. The spawn so produced, apart from rearing further to fry stage and then to fingerling tage for supply, are disposed off at spawn stage also. The FFU is a leading producer of catla fish seed which is in great demand in the region. It is ideal in respect of its location, design, maintenance of breeders, hatching facilities etc. The fisherman of the area have great faith in the quality of seeds provided by the FFU. Many undergraduate and postgraduate Students of Zoology from various colleges of the State Karnataka and neighboring State of Goa pay visit to the FFU every year as part of their practical training in fish culture and breeding aspects. The unit provides good quality of seeds to the farmers in the area who decide to take up fish rearing for additional income at very competitive prices.ICE-CUM-COLD STORAGE PLANT UNITFish is a highly perishable commodity. Its preservation soon after its catch from the water is essential. Icing the fresh fish is the simplest preservation method. In order to meet the ice demand of the fishermen, 5 Tonne capacity Ice Plant was set up in the year 1966. At the same time a 10 tonne capacity cold storage plant was also established. As there is no demand for cold storage space, the plant is idle now. Another ice plant of 10 tonne capacity was set up in the year 1986 which is presently functioning and ice is being marketed throughout the year with peak season falling between February to May.
IRRIGATION WING
|
Tungabhadra River
The River Tungabhadra derives its name from two streams viz., the Tunga, about 147 km (91.6 miles) long and the Bhadra, about 178 Km (110.9 miles) long which rise in the Western Ghats. The river after the influence of the two streams near Shimoga, runs for about 531 Km (330 miles) till it joins the river Krishna at Sangamaleshwaram in Andhra Pradesh. It runs for 382 Km (237 miles) in Karnataka, forms the boundary between Karnataka and Andhra Pradesh for 58 Km (36 miles) and further runs for the next 91 Km (57 miles) in Andhra Pradesh. The total catchment area of the river is 69,552 Sq Km (26,856 Sq miles) up to its confluence with Krishna and it is 28,177 Sq Km (10,880 Sq miles) up to Tungabhadra Dam. It is influenced chiefly by the South-West monsoon. It is a perennial river but the summer flows dwindle to as low as 2.83 to 1.42 cumec (100 to 50 cusec).